Industry Insight
MTC validation failurerework claimgrade mismatchincoming inspectionquality cost
Blog·5 min read·

A $340K Rework Claim Started With One Cert Nobody Checked Against the PO Spec

The customer order specified structural plate to ASTM A572 Grade 60. The fabricator's purchasing team placed the PO with their plate service center. The service center shipped A572 Grade 50 — the grade they had in stock for that thickness. The MTCs that arrived with the shipment clearly showed Grade 50. Nobody compared the MTC grade to the PO grade at receiving.

The shop cut, fit, and welded 180 structural pieces over three weeks. When the customer's inspector arrived for the pre-ship inspection, he pulled the MTCs, compared them to the material call-out on the design documents, and wrote a non-conformance report. Every piece was on hold. The customer rejected the shipment.

The fabricator's total exposure: $340,000.

The Anatomy of the Failure

This failure had three contributing causes, none of them unusual:

The service center substituted without notification. The service center received a PO for A572 Grade 60 and sourced from Grade 50 inventory. Whether this was a misread of the PO, an assumption that Grade 50 was acceptable, or a deliberate swap to clear inventory is unclear. The MTC accurately reflected what was shipped — Grade 50. The substitution was made without notifying the fabricator or requesting approval.

Incoming inspection compared visual appearance, not documentation. The receiving process at the fabricator consisted of counting pieces, checking bundle tags for quantity and size, and filing the MTCs. The MTC review was a scan for legibility, not a comparison against the PO line items. Grade 50 and Grade 60 plate look identical. The receiving clerk had no process for comparing the MTC's stated grade to the PO's specified grade.

The shop assumed incoming inspection meant the material was cleared. Once material cleared receiving and entered the shop floor inventory, fabricators assumed it was correct. Nobody in the cutting, fit-up, or welding stages had reason to re-examine the MTCs. The material had a green "received and inspected" tag.

The root cause was not the service center's substitution. Service centers sometimes make errors. The root cause was the absence of a gate in the receiving process that would have caught the substitution before fabrication began.

The $340,000 Breakdown

Material replacement — $87,000. The Grade 50 plate had to be returned and correct Grade 60 material sourced. With Grade 60 at the required thickness, there was an 8-week lead time for mill production. Expedite fees for partial quantities from alternative sources added $12,000.

Labor — $156,000. All 180 fabricated pieces were rejected. The labor invested in cutting, fit-up, and welding — approximately 2,200 person-hours — was unrecoverable. The fabricator carried those labor costs as a direct loss.

Scrap and disposal — $18,000. The 180 fabricated pieces could not be reworked to Grade 60 specification — grade cannot be upgraded by any fabrication process. The structural pieces were scrapped for melt value, netting a small material credit but incurring handling, cutting, and disposal costs.

Schedule delay penalty — $52,000. The customer contract contained a late delivery clause of $1,000 per calendar day for delays beyond the contractual delivery date. The replacement material lead time plus the fabrication cycle for the replacement pieces resulted in a 52-day delay. The fabricator paid $52,000 in liquidated damages.

Customer relationship remediation — $27,000. This item is harder to quantify but very real. The fabricator's project manager and quality director flew to the customer's facility twice for meetings. The fabricator provided a 30-day complimentary fabrication credit on a future order as a relationship repair gesture. These costs totaled approximately $27,000 in direct and indirect expense.

Total: $340,000. Against a job that was originally a $280,000 contract.

The Process Fix

The fabricator implemented a mandatory MTC-to-PO comparison at receiving within 30 days of the incident. The process change was not expensive:

A one-page comparison form was added to the receiving process. For each MTC received, the form requires the receiving inspector to record: PO number, PO line item material specification and grade, MTC material specification and grade, and sign-off that they match. If they don't match, the material goes on hold and the discrepancy is documented before it leaves the receiving area.

The form takes 3 minutes per MTC. For an operation receiving 40 MTCs per week, that's 2 hours of weekly receiving time. The comparison form is filed with the MTC in the job folder.

In the 18 months following implementation, the form caught four grade mismatches at receiving — all before any fabrication began. None of the four became a quality event. The material was returned, replacement material was sourced, and fabrication proceeded with correct material.

The annual cost of the 2-hour weekly process addition: approximately $5,000 in labor. The cost of the one event that preceded it: $340,000.

The Broader Point

The $340,000 loss was entirely preventable with a 3-minute check at receiving. The check doesn't require expertise, software, or significant process investment. It requires a structured comparison of two data points — what the PO says and what the MTC says — and a rule that material doesn't enter fabrication if those two data points don't match.

Most fabrication operations have no formal gate for this comparison. Incoming inspection confirms the material arrived and the cert came with it. It does not systematically verify that the cert matches what was ordered. The cost of adding that gate is measured in minutes per cert. The cost of not having it is measured in events like this one.

What to Read Next